Uptown Sedona road work nears end2 min read

Vehicles navigate the nor thernmost roundabout in Uptown on March 5. The roundabout was paved last week while the Jordan Road roundabout was paved this week. The Sedona in Motion Uptown projects began last summer and are now approaching their conclusion, with 95% of work finished. The Schnebly Road detour and anti-jaywalking medians are the last major projects the contractor has yet to complete. Photo by David Jolkovski/Larson Newspapers

As temperatures begin to slowly creep upwards and spring break nears, a lot of eyes will be on the construction in Uptown as part of the ongoing Sedona in Motion transpor­tation plan. 

Jason Woods, project manager for Eagle Mountain Construction, said overall things are going well. 

“The uptick in traffic and visitors to Sedona has made things more chal­lenging,” he said. “That, combined with the stage of the project, has made traffic control options limited, which unfortunately made driving condi­tions through town tough there for a few weeks. Now that the majority of the [State Route] 89A corridor has pavement and concrete work is near completion, traffic flow can move as it was intended for the most part.” 

Woods said the biggest delay they’ve faced was the inability to start building the new Schnebly Road roundabout at the same time as they did the Jordan roundabout. This was a four-month delay completely out of Eagle Mountain’s control that had a major impact on the schedule, he said. Their crews were able to make up most of that time with “hard work and putting in the extra time needed.” 

The plan all along has been to have the majority of the more involved aspects of the project completed prior to spring break. 

Advertisement

“Our crews really put an outstanding effort in order to get things ready to pave in short order, especially after the last rain damaged quite a bit of grade that had to be fixed,” he said. “For the most part major paving and concrete is 95% complete in the 89A corridor. There are two areas left — one at the base of Apple Road and another small section of asphalt at the west side of mid block left. We will do those after the spring break rush dies down.” 

In terms of feedback during the construction phase, Woods said it’s been mixed and that he encourages merchants and residents to come out to their weekly Monday morning meet-ups. By doing so, everyone can get accurate information directly from them. 

“Comments have overall been really positive, especially from merchants that we are fortunate to meet with,” he said. “Most nega­tive comments seem to be in regards to the design itself which we don’t have much to do with. The nega­tive comments I’ve seen have been on social media and those outlets. Unfortunately those places tend to run rampant with untrue assumptions.” 

Crews are wrapping up some paving on the Schnebly Road connector and finished the Jordan roundabout last week. 

“Over the next few weeks we will be working on the median wall and landscape in select areas, but are trying to limit the disturbance,” he said. “All of this work will extend for the next few months but will not have near the impact of the concrete and paving work.” 

Ron Eland

Ron Eland has been the assistant managing editor of the Sedona Red Rock News for the past seven years. He started his professional journalism career at the age of 16 and over the past 35 years has worked for newspapers in Nevada, Hawaii, California and Arizona. In his free time he enjoys the outdoors, sports, photography and time with his family and friends.

- Advertisement -
Ron Eland has been the assistant managing editor of the Sedona Red Rock News for the past seven years. He started his professional journalism career at the age of 16 and over the past 35 years has worked for newspapers in Nevada, Hawaii, California and Arizona. In his free time he enjoys the outdoors, sports, photography and time with his family and friends.